Please see our revised list of construction activities for the next two weeks*-


*These areas are on the boundary between ANC 4B03 (Commissioner Smith) and 4B07 (Commissioner 4B07).


Week of January 30


6300 – 6500 blocks of 3rd Street NW

• Monday, January 30 – Friday, February 3

We are performing the installation of a new water main at this location throughout this week.


Week of February 6


6300 – 6500 blocks of 3rd Street NW

• Monday, February 6 – Friday, February 10

We will continue with the installation of a new water main at this location throughout next week, as well.


Please keep in mind that these construction activities are highly dependent upon favorable weather conditions.

8 views0 comments

Recent Posts

See All

DPW Update

The recent winter weather event has made it unsafe for DPW staff and vehicles to maneuver through certain alleyways. As a result, some...

January 7th Update

A few more updates for Tuesday Jan 7th: DC Government Offices Expected to be open at 10am on Tuesday Jan 7th DCPS Update: Due to weather...