Roadway Improvement Project - Kansas Avenue between North Dakota Avenue NW and Longfellow Street NW

Writer's picture: Tiffani JohnsonTiffani Johnson

I have been advised that there is an roadway improvement project along Kansas Avenue between Longfellow and North Dakota Avenue NW beginning on or about November 15, 2021.


The work is being conducted in two phases:


Phase 1 - concrete work to take approximately two weeks, weather permitting. This will include the upgrading of wheelchair ramps, sidewalk, curb and gutter repairs.


Phase 2 - asphalt roadway paving


Curbside parking will be restricted during the construction. At least one lane of traffic will be maintained through the construction area. The contractor is allowed to work between 7am-7pm Monday-Saturday. Temporary "EMERGENCY NO PARKING" signage will be placed 72 hours before the work is scheduled to commence.


If you have additional questions, please reach out to me at 4B06@anc.dc.gov, 202.271.3710 (cell) or you can reach the DDOT Engineer, Delante Toyer at delanta.toyer@dc.gov, 202391.8236 (cell) or 202.671.4572 (office).

5 views0 comments

Recent Posts

See All

DPW Update

The recent winter weather event has made it unsafe for DPW staff and vehicles to maneuver through certain alleyways. As a result, some...

January 7th Update

A few more updates for Tuesday Jan 7th: DC Government Offices Expected to be open at 10am on Tuesday Jan 7th DCPS Update: Due to weather...

Comments


 © 2023 by Luhring Media.                           Proudly created with Wix.com

4B06 Logo.png
bottom of page